← Tenders / JTF Failte Ireland and Laois County Council Rock of Dunamase Car Park
Awarded Construction & Civil Engineering Works Open

JTF Failte Ireland and Laois County Council Rock of Dunamase Car Park

Value

€100k

Deadline

06 Mar

Construction of the Rock of Dunamase Car Park for Laois County Council

📍 Laois

Construction of the Rock of Dunamase Car Park for Laois County Council

Risks & flags

  • Qualification gate for turnover
  • Two-step tender process
  • Ambiguity in ITT requirements

Briefing

AI-generated analysis of the documents. Check the official notice and any amendments for current submission details.

1. At a glance

Field Detail
Buyer Laois County Council
Title JTF Failte Ireland and Laois County Council Rock of Dunamase Car Park
CPV / category works
Estimated value 100000.00
Per-year (if multi-year) not stated
Procedure type not stated
Lots not stated
Location Ireland
Contract length 6 months
Submission deadline 2026-03-06T00:00:00+00:00
Go-live / start not stated

2. Scope of Work

Laois County Council ran this procurement for “JTF Failte Ireland and Laois County Council Rock of Dunamase Car Park” as an operational contract requiring implementation and sustained service execution. The extracted pack showed qualification-stage material with references to later ITT technical depth; practical activity therefore centred on building, integrating, and operating the specified service stack with compliant reporting and handover obligations where stated. Constituent activities and named work elements in the supplied extracts:

  • ctory Production Control (FPC) system in accordance with IS EN 13108-21 for each manufacturing facility to be used during the contract
  • system in accordance with IS EN 13108-21 for each manufacturing
  • Control (FPC) system in accordance with IS EN 13108-21
  • Control (FPC) system in accordance with IS EN 13108-21 for each manufacturing facility to be used
  • system in accordance with IS EN 13108
  • It is a condition of the mini-competition that supply (and place) contracts can only be allocated to
  • contractors/suppliers where all relevant supporting documentation has been submitted.
  • Where the contract awarded requires supply and delivery by the quarry of materials to a Council site, all delivery
  • circumstance where trucks being used by a quarry to supply materials to a Council site are found to be in breach
  • of this requirement, the supplying quarry may be excluded from supplying further materials under this mini-tender.
  • Making Materials and Ancillary Works for Local Authorities – Supply and Place (Lot 2).
  • Relevant payments shall be subject to Irish ‘Professional Services Withholding Tax’ at the prevailing rate Non-binding monetary references in the source were treated as context only and were not used as qualification thresholds.

3. Background & buyer context

The buyer context reflected a formal Irish public-procurement route, with pre-qualification used to control entry into the tender stage.

  • Contracting Authority. Replacement personnel must be of equal or better standing that the existing personnel in
  • management, project programme, resourcing proposals and allowable project duration.

4. Eligibility & selection criteria

  • Turnover requirement — — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.
  • Insurance — — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.; ) Minimum indemnity limit for employer’s liability insurance €13,000,000 for any one event ; 4 Maximum levels of excess for * insurance of the Works and goods and materials for the Works €10,000 * public liability €6,500[9] * employer’s liability €6,500[10]
  • Certifications — not specified for this tender
  • Past experience — not specified for this tender
  • Personnel — not specified for this tender
  • Geographic / facility constraints — not specified for this tender Additional binding lines surfaced in the deterministic extract:
  • — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.
  • ) Minimum indemnity limit for employer’s liability insurance €13,000,000 for any one event
  • 4 Maximum levels of excess for * insurance of the Works and goods and materials for the Works €10,000 * public liability €6,500[9] * employer’s liability €6,500[10]
  • ) Minimum indemnity limit for employer’s liability insurance €13,000,000 for any one event 10
  • 4 Maximum levels of excess for  insurance of the Works and goods and materials for the Works €10,000  public liability €6,5009 7 If no percentage specified, 10% applie
  • 6 19/07/2023 6  employer’s liability €6,50010 12

5. Award criteria & scoring

Criterion Weight (%) Sub-criteria Pass/fail threshold
The lowest total cost tendered for completion of the works will be awarded 100% 100% not stated not stated
The lowest total cost tendered for completion of the works will be awarded 100% 100% not stated not stated
The documents indicated a staged process (qualification, then tender). Any explicit MEAT split is captured above where a numeric line was visible; otherwise it remained not specified in the provided text extract.

6. Submission requirements

  • Method statement / response document (template/page limits) — not specified in extract.
  • CVs (page count, named roles) — not specified in extract.
  • Pricing schedule (format/template) — expected at ITT stage.
  • Case studies (number/value range) — client references/comparable project evidence was referenced.
  • Declarations (ESPD/Bona Fides/Tax/COI) — ESPD/declaration/statement-of-confirmation language was present.
  • Mandatory site visit — not specified in extract.
  • Submission portal and formatting — eTenders portal and PDF electronic copies were referenced. Submission-related source lines:
  • [RODCP Instructions To Tenderers.pdf] Laois County Council
  • [RODCP Instructions To Tenderers.pdf] contract for the Works
  • [RODCP Instructions To Tenderers.pdf] LoCall: 1890 220 222
  • contractors/suppliers where all relevant supporting documentation has been submitted.
  • that subject to available budget and pricing Laois County Council reserves the right to omit works from the
  • [RODCP Instructions To Tenderers.pdf] ........................................................................................................................................... 23

7. Key dates & process

Milestone Date
RFT issued not specified
Clarification deadline not specified
Mandatory site visit not specified
Tender deadline (date + time) 2026-03-06T00:00:00+00:00
Expected award not specified
Contract start not specified
Go-live / mobilisation not stated
Date surfaced in documents 2026-03-06T00:00:00+00:00
Date surfaced in documents April 2025
Date surfaced in documents May 2026
Date surfaced in documents Regulations 2006

8. Contract terms that matter

Contract duration in the extract: 6 months. Payment cycle, SLA/KPI schedule, and penalty regime were not fully disclosed in the snippets unless listed below.

  • VERIFIED PHRASES (deterministic regex extract from the documents — treat as authoritative for numerical claims)
  • lace arrangements to complete the Works within 6 months after the termination, the Employer’s Representative will give the above certificate to
  • the Works within 12 months after the termination, the Contractor’s payment under this clause
  • e Schedule says that a performance bond is required, within 7 days after the Employer sends
  • When a payment is to be made, not later than 5 days after the date agreed between the
  • Within 14 days of receiving the payment claim notice,
  • n to put in place arrangements to complete the Works within 6 months after the termination, the Employer’s R
  • the Works within 12 months after the termination, the Contractor’s

9. Risks, red flags & unusuals

  • Qualification gate: the deterministic extract included a turnover threshold line (— use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.), which can materially narrow bidder pool composition.
  • The two-step process (PQQ then ITT) shifted effort to compliance evidence early, with competitive scoring detail potentially deferred.
  • Technical and contractual granularity appeared ITT-dependent, increasing ambiguity at qualification stage for non-incumbent bidders.

10. SME fit assessment

This competition looked most accessible to firms with established public-sector tender capability, documented financial capacity, and direct operational experience in the relevant service category.

  • Credible bidder profile — mid-sized to large specialist with formal QA/compliance process.
  • Consortium / sub-contracting — not clearly specified in extract.
  • Indicative bid-prep effort — 6 to 12 working days for evidence collation, form completion, and review cycles at PQQ level.
  • Pwin signal — strongest for bidders with reusable qualification artefacts, comparable references, and low-friction mobilisation capability.

11. Where to dig deeper

  • Source RFT/PQQ filenames: RODCP Instructions To Tenderers.pdf, Schedule says that a performance bond is required, within 7 days after the Employer send, Appendix 3 ..............................................................................
  • eTenders CFT / notice reference: not specified in extract.
  • Clarification contact / portal: [email protected].
  • Key attachments to prioritise: Schedule, Schedule (Volume B);, Schedule);.

This tender has been awarded

Can you bid?

Required certifications

  • EN 13108

Public liability insurance

€6,500

Scoring

Most Economically Advantageous Tender

Lots (1)

Lot 1: Rock of Dunamase Car Park Construction

Construction of surface wearing course, basecourse, and binder layer for the Rock of Dunamase Car Park.

Documents (10)

PDF

RODCP Instructions To Tenderers.pdf

630.5 KB · RFT / Invitation to Tender

PDF

PW-CF6-v1.14-19-07-2023.pdf

612.0 KB · Contract / Agreement / Terms

PDF

PQQ Construction.pdf

377.5 KB · Form / Declaration / Certificate

DOCX

RODCP Form of Tender and Schedule.docx

58.7 KB · Form / Declaration / Certificate

PDF

RODCP Form of Tender and Schedule.pdf

270.2 KB · Form / Declaration / Certificate

PDF

ROD Car Park- Proposed Pavement Layout 120226A.pdf

1.9 MB · Drawing / Plan / Layout

PDF

RODCP Prelim Safety and Health Plan.pdf

490.1 KB · Other

PDF

Procedural Agreement for use of Contractors.pdf

45.0 KB

DOCX

RODCP Instructions To Tenderers Appendices Only.docx

2.9 MB · Appendix / Annex

PDF

RODCP Instructions To Tenderers Appendices Only.pdf

142.7 KB · Appendix / Annex

Original notice text

This tender involves the construction and operational management of the Rock of Dunamase Car Park, requiring compliance with specific reporting and service execution standards.

AI analysis updated 4 months ago

Bid ↗
Details

Value

€100k

Deadline

06 Mar

View on eTenders ↗

Location

Rock of Dunamase Car Park

Procedure

Open

Clarification

25 Feb 2026

eTenders ID

7527983

✦ Ask AI about this tender

Ask AI

Knows this tender's documents

Is this a good fit for us?
Based on the deadline, buyer, and eligibility requirements in the tender documents, here's a quick read on fit — with citations back to the exact clause 1 so you can verify it yourself.

Example only — sign up to ask about this tender