EST WORKS - Connolly Hospital Generator Resilience Project (including PSCS)
Value
€3.0m
Deadline
31 May
31 May 2024
Value
€3.0m
Deadline
31 May
Generator resilience project at Connolly Hospital for Health Service Executive.
Generator resilience project at Connolly Hospital for Health Service Executive.
Bidder profile
Mid-sized to large firms with experience in public sector projects and generator installations.
Risks & flags
- Qualification gate
- Two-step process
- Technical ambiguity
Briefing
AI-generated analysis of the documents. Check the official notice and any amendments for current submission details.
1. At a glance
| Field | Detail |
|---|---|
| Buyer | Health Service Executive (HSE) |
| Title | EST WORKS - Connolly Hospital Generator Resilience Project (including PSCS) |
| CPV / category | works |
| Estimated value | 3000000.00 |
| Per-year (if multi-year) | not stated |
| Procedure type | not stated |
| Lots | not stated |
| Location | Ireland |
| Contract length | 8 months |
| Submission deadline | 2024-05-31T11:00:00+00:00 |
| Go-live / start | not stated |
2. Scope of Work
Health Service Executive (HSE) ran this procurement for “EST WORKS - Connolly Hospital Generator Resilience Project (including PSCS)” as an operational contract requiring implementation and sustained service execution. The extracted pack showed qualification-stage material with references to later ITT technical depth; practical activity therefore centred on building, integrating, and operating the specified service stack with compliant reporting and handover obligations where stated. Constituent activities and named work elements in the supplied extracts:
- Buyer: Health Service Executive (HSE)
- rer shall be required to supply its Tax Clearance Access Number and Tax Reference Number to facilitate online verification of their tax status by
- The Project 2 NEW STANDBY GENERATOR SYSTEMS AND ASSOCIATED ELECTRICAL AND BUILDERS WORK. AT CONNOLLY HOSPITAL
- Regarding: The Project NEW STANDBY GENERATOR SYSTEMS AND ASSOCIATED ELECTRICAL AND BUILDERS WORK. AT CONNOLLY HOSPITAL
- Minimum indemnity limit for Public liability insurance: €6,500,000[7] for any one event, but this limit may be on an annual aggregate basis for products liability, collapse, vibration, subsidence, removal and weakening of supports and sudden and accidental pollution.
- [FTS-5-v2.6-17-07-2023-1.docx] an annual aggregate basis for products liability, collapse, vibration, subsidence, removal and weakening of supports and sudden and accidental pollution.
- Persons under a contract of service or apprenticeship with the insured
- Persons under a contract of service or apprenticeship with the insured.
- Effecting or maintenance of insurance of or in connection with the provision of finance or advice on financial matters
- Utilities means conducting media and apparatus for water, sewage, electricity, gas, oil, telecommunications, data, steam, air, or other services, and associated apparatus and structures.
- The arbitration rules are the Capital Works Management Framework (CWMF) Arbitration Rules for use with Public Works and Construction Services Contracts (AR1) published on http://constructionprocurement.gov.ie/arbitration-rules/ on the date 10 days before the latest date for submission of Tenders for this contract (disregarding any amendments posted on that date).
- The Contractor’s agent[19] in the Republic of Ireland for service of legal process is: Non-binding monetary references in the source were treated as context only and were not used as qualification thresholds.
3. Background & buyer context
The buyer context reflected a formal Irish public-procurement route, with pre-qualification used to control entry into the tender stage.
- Property of the insured or in the insured’s custody or control other than existing premises and their contents temporarily occupied for the purposes of the Works
- K Delay Events, Compensation Events, Programme Contingency, Delay Costs, Adjustments(Sub-clauses 9.3, 9.4, 10.1, 10.6, 10.7)
-
- The programme contingency is Site Working Days of delay caused by Compensation Events.
4. Eligibility & selection criteria
- Turnover requirement — — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.
- Insurance — — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.; Minimum indemnity limit for Public liability insurance: €6,500,000[7] for any one event, bu; Minimum indemnity limit for Employers’ liability insurance: €13,000,000[8] for any one event
- Certifications — not specified for this tender
- Past experience — not specified for this tender
- Personnel — not specified for this tender
- Geographic / facility constraints — not specified for this tender Additional binding lines surfaced in the deterministic extract:
- — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.
- Minimum indemnity limit for Public liability insurance: €6,500,000[7] for any one event, bu
- Minimum indemnity limit for Employers’ liability insurance: €13,000,000[8] for any one event
- Maximum excess for Public liability: €10,000~~[10]~~ in respect of p
5. Award criteria & scoring
| Criterion | Weight (%) | Sub-criteria | Pass/fail threshold |
|---|---|---|---|
| The Contractor’s tendered percentage addition to costs of labour *(If negative 0% not stated not stated | |||
| The Contractor’s tendered percentage addition to costs of labour *(If negative 0% not stated not stated | |||
| The Contractor’s tendered percentage addition to costs of materials *(If negat 0% not stated not stated | |||
| The Contractor’s tendered percentage addition/deduction to costs of plant *(A 50% not stated not stated | |||
| The documents indicated a staged process (qualification, then tender). Any explicit MEAT split is captured above where a numeric line was visible; otherwise it remained not specified in the provided text extract. |
6. Submission requirements
- Method statement / response document (template/page limits) — not specified in extract.
- CVs (page count, named roles) — not specified in extract.
- Pricing schedule (format/template) — expected at ITT stage.
- Case studies (number/value range) — client references/comparable project evidence was referenced.
- Declarations (ESPD/Bona Fides/Tax/COI) — ESPD/declaration/statement-of-confirmation language was present.
- Mandatory site visit — not specified in extract.
- Submission portal and formatting — not specified in extract. Submission-related source lines:
- ect item description and the difference for an item in, or that should have been in, the Pricing Document is more than €500. No Yes
- Deliver a Generator project within 8 months, the main contractor must submit a minimum of two previous projects that demonstrate they have completed Generator projects within 8 months of them starting
- e that any variant tenders are permitted, a variant tender must comply with the minimum requirements set out in the Particulars If so stated in the Particulars, variant tenders may be submitted only by a Candidate who also submits a standard tender
- ough relevant projects submitted for each Candidate team member and their maximum points are set out in the table below 10](#_Toc144211191)
- ough relevant projects submitted for each Candidate team member and their maximum points are set out in the table below
- onsortium Member/Sub-Consultant Proposal & Declarations (MEMBER Consortium Member/Sub-Consultant Proposal & Declarations (MEMBER)*’ which shall b
7. Key dates & process
| Milestone | Date |
|---|---|
| RFT issued | not specified |
| Clarification deadline | not specified |
| Mandatory site visit | not specified |
| Tender deadline (date + time) | 2024-05-31T11:00:00+00:00 |
| Expected award | not specified |
| Contract start | not specified |
| Go-live / mobilisation | not stated |
| Date surfaced in documents | 2024-05-31T11:00:00+00:00 |
| Date surfaced in documents | 17 July 2023 |
| Date surfaced in documents | March 2021 |
| Date surfaced in documents | August 2021 |
8. Contract terms that matter
Contract duration in the extract: 8 months. Payment cycle, SLA/KPI schedule, and penalty regime were not fully disclosed in the snippets unless listed below.
- VERIFIED PHRASES (deterministic regex extract from the documents — treat as authoritative for numerical claims)
- ect item description and the difference for an item in, or that should have been in, the Pricing Document is more than €500. No Yes
- Minimum amount for interim payments, except release of retention, € 0.00 [14]
- Minimum amount for interim payments, except release of retention, € 0
- t is aware of the multiple participation by the relevant member and that it has been brought to the attention of all the consortium/joint venture
- Within 3 months after receipt of the Contractor’s final statement, the Employer’s
- lace arrangements to complete the Works within 6 months after the termination, the Employer’s Representative shall issue this certificate as
- (b) expiry of at least 21 days written notice to terminate this Tender
9. Risks, red flags & unusuals
- Qualification gate: the deterministic extract included a turnover threshold line (— use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.), which can materially narrow bidder pool composition.
- The two-step process (PQQ then ITT) shifted effort to compliance evidence early, with competitive scoring detail potentially deferred.
- Technical and contractual granularity appeared ITT-dependent, increasing ambiguity at qualification stage for non-incumbent bidders.
10. SME fit assessment
This competition looked most accessible to firms with established public-sector tender capability, documented financial capacity, and direct operational experience in the relevant service category.
- Credible bidder profile — mid-sized to large specialist with formal QA/compliance process.
- Consortium / sub-contracting — allowed or addressed in the extracts (Appendix references and reliance provisions).
- Indicative bid-prep effort — 6 to 12 working days for evidence collation, form completion, and review cycles at PQQ level.
- Pwin signal — strongest for bidders with reusable qualification artefacts, comparable references, and low-friction mobilisation capability.
11. Where to dig deeper
- Source RFT/PQQ filenames: FTS-5-v2.6-17-07-2023-1.docx, Where Civil Engineering Standard Method of Measurement 3 is selected from the drop down menu above it shall be the 3rd Edition as
[FTS-5-v2.6-17-07-2023-1.docx, ITT-W1-v2.3-07-01-2022.docx.
- eTenders CFT / notice reference: not specified in extract.
- Clarification contact / portal: [email protected].
- Key attachments to prioritise: Schedule and, Schedule, part 3D is* *“1, ITT within 2 weeks of the completion of the SAQ.
This tender has been awarded
- De Power Solutions Ltd · 09 Oct 2025
Can you bid?
Minimum turnover
€4,500,000
Public liability insurance
€6,500,000
Scoring
Most Economically Advantageous Tender
Technical Merit
Relevant Experience
Price
Lots (1)
Installation of two LV generators and retrofit of two substations at Connolly Hospital.
Documents (38)
FTS-5-v2.6-17-07-2023-1.docx
92.8 KB · RFT / Invitation to Tender
ITT-W1-v2.3-07-01-2022.docx
114.5 KB · RFT / Invitation to Tender
PIM_&_SAQ_Connolly_Generator_Res_.docx
105.8 KB · RFT / Invitation to Tender
Contract Notice_Connolly_Generator_Resilience.docx
17.7 KB · Contract / Agreement / Terms
PW-CF5-v2.4-05-06-2019.pdf
816.2 KB · Contract / Agreement / Terms
QW1 SUPPLEMENT 3.4.1.docx
34.3 KB · Form / Declaration / Certificate
QW1 SUPPLEMENT 3.4.2.docx
34.4 KB · Form / Declaration / Certificate
23618-VCE-XX-00-DR-E-100.pdf
324.3 KB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-1000.pdf
706.6 KB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-1001.pdf
1.0 MB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-101.pdf
411.7 KB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-102.pdf
370.5 KB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-103.pdf
377.3 KB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-150.pdf
433.6 KB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-151.pdf
415.1 KB · Drawing / Plan / Layout
23618-VCE-XX-00-DR-E-151A.pdf
253.2 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-152.pdf
526.4 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-153.pdf
263.0 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-154.pdf
350.0 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-155.pdf
268.1 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-156.pdf
336.8 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-157.pdf
380.7 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-158.pdf
365.3 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-DR-E-159.pdf
280.1 KB · Drawing / Plan / Layout
23618-VCE-XX-XX-RG-E-0001.pdf
334.8 KB · Drawing / Plan / Layout
23618 Summary of Tender.doc
161.5 KB
23618-VCE-XX-XX-SP-E-0001.pdf
2.3 MB
QW1 APPENDIX A.docx
18.2 KB · Appendix / Annex
QW1 APPENDIX A1.docx
15.3 KB · Appendix / Annex
QW1 APPENDIX B1.docx
17.7 KB · Appendix / Annex
QW1 APPENDIX B2.docx
14.0 KB · Appendix / Annex
QW1 APPENDIX B3.docx
19.8 KB · Appendix / Annex
QW1 APPENDIX C1.doc
46.0 KB
QW1 APPENDIX C3.docx
21.6 KB · Appendix / Annex
QW1 APPENDIX C4.docx
21.6 KB · Appendix / Annex
QW1 APPENDIX D.docx
46.1 KB · Appendix / Annex
QW1 APPENDIX G.docx
15.9 KB · Appendix / Annex
QW1 APPENDIX H.docx
17.2 KB · Appendix / Annex
Original notice text
The project involves the installation of two new standby generator systems and associated electrical and builders work at Connolly Hospital, aimed at enhancing the hospital's generator resilience.
AI analysis updated 4 months ago
Value
€3.0m
Deadline
31 May
Location
Connolly Hospital, Ireland
Procedure
Restricted
Clarification
22 May 2024
eTenders ID
3388844