The recorded submission deadline has passed. Find open opportunities. Check the official notice for amendments.
← Tenders / Remedial fire works, upgrade of heating and hydrotherapy pool at Central Remedial Clinic Clontarf
Closed Building Services & Maintenance Works Open

Remedial fire works, upgrade of heating and hydrotherapy pool at Central Remedial Clinic Clontarf

Value

€450k

Deadline

19 Jan

Upgrade of heating and hydrotherapy pool at Central Remedial Clinic Clontarf

SME fit: Medium Bid effort: Medium

Upgrade of heating and hydrotherapy pool at Central Remedial Clinic Clontarf

Bidder profile

Mid-sized to large firms with experience in public sector projects and compliance processes.

Risks & flags

  • Qualification gate turnover threshold
  • Two-step process
  • Technical granularity dependent on ITT

Briefing

AI-generated analysis of the documents. Check the official notice and any amendments for current submission details.

1. At a glance

Field Detail
Buyer Central Remedial Clinic
Title Remedial fire works, upgrade of heating and hydrotherapy pool at Central Remedial Clinic Clontarf
CPV / category works
Estimated value 450000.00
Per-year (if multi-year) not stated
Procedure type not stated
Lots not stated
Location Ireland
Contract length 10 years
Submission deadline 2024-01-19T12:00:00+00:00
Go-live / start not stated

2. Scope of Work

Central Remedial Clinic ran this procurement for “Remedial fire works, upgrade of heating and hydrotherapy pool at Central Remedial Clinic Clontarf” as an operational contract requiring implementation and sustained service execution. The extracted pack showed qualification-stage material with references to later ITT technical depth; practical activity therefore centred on building, integrating, and operating the specified service stack with compliant reporting and handover obligations where stated. Constituent activities and named work elements in the supplied extracts:

  • Sector: Building Services & Maintenance
  •  Insulated Pipe Support Inserts shall be a minimum of 99 mm in length to allow for
  • supply in accordance with the parameters laid down in BS EN 60598-2-22
  • system/fire ceilings & general building works to existing Health Care Facility
  • heating system/fire ceilings & general building works to existing Health
  • Scope of works of specialist pool contractor for the Hydro pool room.- Bracken Pool Services
  • annual aggregate basis for products liability, collapse, vibration, subsidence, removal and weakening of supports
  •  Persons under a contract of service or apprenticeship with the insured
  •  Persons under a contract of service or apprenticeship with the insured.
  •  Effecting or maintenance of insurance of or in connection with the provision of finance or advice on financial
  • Radon System, Tanking Membranes Certification.
  • steam, air, or other services, and associated apparatus and structures. Non-binding monetary references in the source were treated as context only and were not used as qualification thresholds.

3. Background & buyer context

The buyer context reflected a formal Irish public-procurement route, with pre-qualification used to control entry into the tender stage.

  • Various fire stopping works to existing fire walls, installation of new heating
  • system/fire ceilings & general building works to existing Health Care Facility
  • Various fire stopping works to existing fire walls, installation of new
  • heating system/fire ceilings & general building works to existing Health

4. Eligibility & selection criteria

  • Turnover requirement — — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.
  • Insurance — — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.; 4 27/01/2014 16 RESPONSE: NOT REQUIRED (i) The level of cover as stated here: Minimum level of Professional Indemnity Insurance required for - Not Applicable €CA Entry CA Note: State the minimum cover proportionate to the size of the project (default level is €2.5m) (ii) The excess as stated here: Max; Minimum level of Public Liability Insurance required in respect of any one accident below which the Works Contractor and as PSCS will bear the cost: €6500000 CA Entry: State above the minimum level
  • Certifications — not specified for this tender
  • Past experience — The minimum average Construction Works turnover required over the last three years is €1.0 million per year (Ex Vat); 4 27/01/2014 16 RESPONSE: NOT REQUIRED (i) The level of cover as stated here: Minimum level of Professional Indemnity Insurance required for - Not Applicable €CA Entry CA Note: State the minimum cover proportionate to the size of the project (default level is €2.5m) (ii) The excess as stated here: Max
  • Personnel — not specified for this tender
  • Geographic / facility constraints — not specified for this tender Additional binding lines surfaced in the deterministic extract:
  • — use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.
  • The minimum average Construction Works turnover required over the last three years is €1.0 million per year (Ex Vat)
  • 4 27/01/2014 16 RESPONSE: NOT REQUIRED (i) The level of cover as stated here: Minimum level of Professional Indemnity Insurance required for - Not Applicable €CA Entry CA Note: State the minimum cover proportionate to the size of the project (default level is €2.5m) (ii) The excess as stated here: Max
  • Minimum level of Public Liability Insurance required in respect of any one accident below which the Works Contractor and as PSCS will bear the cost: €6500000 CA Entry: State above the minimum level
  • 4 27/01/2014 17 Minimum level of Employer’s Liability Insurance required in respect of any one accident below which the Works Contractor and as PSCS will bear the cost: €13000000 No excess for any one event Tenderer
  • Minimum Indemnity Limit for Public Liability Insurance €6,500,000 for any one event

5. Award criteria & scoring

Criterion Weight (%) Sub-criteria Pass/fail threshold
Quality not stated Methodology / implementation detail not stated in extract not stated
Price not stated Pricing basis not stated in extract not stated
The documents indicated a staged process (qualification, then tender). Any explicit MEAT split is captured above where a numeric line was visible; otherwise it remained not specified in the provided text extract.

6. Submission requirements

  • Method statement / response document (template/page limits) — not specified in extract.
  • CVs (page count, named roles) — not specified in extract.
  • Pricing schedule (format/template) — expected at ITT stage.
  • Case studies (number/value range) — client references/comparable project evidence was referenced.
  • Declarations (ESPD/Bona Fides/Tax/COI) — not specified in extract.
  • Mandatory site visit — not specified in extract.
  • Submission portal and formatting — eTenders portal and PDF electronic copies were referenced. Submission-related source lines:
  • the Pricing Document is more than €500.
  • The minimum requirements under this criteria is the submssion of 2 CV's which shall include a CV for (1)
  • [FTS-5-v2.6-17-07-2023.pdf] Tender and Schedule for Public Works Contract for MINOR Building or Civil Engineering Works Designed by the Employer
  • [FTS-5-v2.6-17-07-2023.pdf] on Ave,
  • Designed by the Employer, the Works Requirements, the Pricing Document, all as amended by any supplemental
  • We submit with this Tender the completed Pricing Document and Schedule and Works Proposals which form part of

7. Key dates & process

Milestone Date
RFT issued not specified
Clarification deadline not specified
Mandatory site visit not specified
Tender deadline (date + time) 2024-01-19T12:00:00+00:00
Expected award not specified
Contract start not specified
Go-live / mobilisation not stated
Date surfaced in documents 2024-01-19T12:00:00+00:00
Date surfaced in documents 17 January 2022
Date surfaced in documents 1 June 2002
Date surfaced in documents 07 December 2022

8. Contract terms that matter

Contract duration in the extract: 10 years. Payment cycle, SLA/KPI schedule, and penalty regime were not fully disclosed in the snippets unless listed below.

  • VERIFIED PHRASES (deterministic regex extract from the documents — treat as authoritative for numerical claims)
  •  Insulated Pipe Support Inserts shall be a minimum of 99 mm in length to allow for
  • Constructed from mild steel and hot dipped galvanised to BS EN 10346:2009
  • Constructed from mild steel and hot dipped galvanised to EN 10346:2009 complete with
  • Within 3 months after receipt of the Contractor’s final statement, the Employer’s
  • lace arrangements to complete the Works within 6 months after the termination, the Employer’s Representative shall issue this certificate as
  • workmanship within 12 months of the handing over and acceptance of the installation by
  • the date 10 days before the last day for receipt of the

9. Risks, red flags & unusuals

  • Qualification gate: the deterministic extract included a turnover threshold line (— use these verbatim for insurance / turnover. If a category (insurance, turnover) has no entry here, treat it as 'not specified' for THIS tender.), which can materially narrow bidder pool composition.
  • The two-step process (PQQ then ITT) shifted effort to compliance evidence early, with competitive scoring detail potentially deferred.
  • Technical and contractual granularity appeared ITT-dependent, increasing ambiguity at qualification stage for non-incumbent bidders.

10. SME fit assessment

This competition looked most accessible to firms with established public-sector tender capability, documented financial capacity, and direct operational experience in the relevant service category.

  • Credible bidder profile — mid-sized to large specialist with formal QA/compliance process.
  • Consortium / sub-contracting — allowed or addressed in the extracts (Appendix references and reliance provisions).
  • Indicative bid-prep effort — 6 to 12 working days for evidence collation, form completion, and review cycles at PQQ level.
  • Pwin signal — strongest for bidders with reusable qualification artefacts, comparable references, and low-friction mobilisation capability.

11. Where to dig deeper

  • Source RFT/PQQ filenames: not later than 5 days after the date agreed between the
  • Within 14 days of receipt of the payment claim notice
  • pay the amount due on the invoice within 21 days after receiving the invoice
  • If, within 14 days of the issue of the certificate of Subs
  • 3 within 21 days after receiving
  • 3 within 21 days after receiving the invoice [less any a

TENDER DOCUMENTS [FTS-5-v2.6-17-07-2023.pdf, FTS-5-v2.6-17-07-2023.pdf, Where Agreed Rules of Measurement 4 is selected from the drop down menu above it shall be as amended by Supplement 1, Issue 2. Where Civil Engineering Standard Method of Measurement 3 is selected from the drop down menu above it shall be the 3rd Edition as amended in accordance with Section 5.2 of Guidance Note GN 1.5.3 of the

[FTS-5-v2.6-17-07-2023.pdf.

  • eTenders CFT / notice reference: not specified in extract.
  • Clarification contact / portal: [email protected].
  • Key attachments to prioritise: Schedule and, scheduled to suit the Employer, Schedule for Public Works Contract for MINOR Building or Civil Engineering Works Designe.

Can you bid?

Required certifications

  • ISO 9001
  • Safe-T-Cert

Minimum turnover

€1,000,000

Public liability insurance

€6,500,000

Professional indemnity insurance

€2,500,000

Scoring

Most Economically Advantageous Tender

Documents (70)

PDF

3079-E-SP-001 Electrical Particular Specification.pdf

1021.4 KB · Specification

PDF

3079-M-BMS-001 Vol A BMS Points List.pdf

713.9 KB · Specification

PDF

3079-M-GSP-001 Vol A Mechanical General Specification.pdf

3.3 MB · Specification

PDF

3079-M-SCH-001 Mechanical Equipment Schedule.pdf

1.1 MB · Specification

PDF

3079-M-SP-001 Mechanical Particular Specification.pdf

1.8 MB · Specification

PDF

Preliminary Health & Safety Plan.pdf

381.5 KB · Specification

PDF

FTS-5-v2.6-17-07-2023.pdf

446.5 KB · RFT / Invitation to Tender

PDF

ITT-W2.pdf

344.5 KB · RFT / Invitation to Tender

PDF

3079-BW-SCH-001.pdf

679.0 KB · Pricing / BOQ / Schedule of Rates

PDF

3079-E-PS-001 Electrical Services Pricing Schedule.pdf

446.9 KB · Pricing / BOQ / Schedule of Rates

PDF

3079-E-SCH-001 Electrical Lighting Schedule.pdf

404.9 KB · Pricing / BOQ / Schedule of Rates

PDF

3079-M-PS-001 Mechanical Services Pricing Schedule.pdf

250.0 KB · Pricing / BOQ / Schedule of Rates

PDF

Important Note Re. Pricing Document.pdf

174.4 KB · Pricing / BOQ / Schedule of Rates

PDF

Volume C Pricing Document CRC Alterations 2023.pdf

1.3 MB · Pricing / BOQ / Schedule of Rates

DOCX

Apointment of PSCS MF1.10 (PWCF 1-5).docx

54.0 KB · Contract / Agreement / Terms

PDF

Contractor Insurance Questionnaire.pdf

102.4 KB · Contract / Agreement / Terms

PDF

PW-CF5.pdf

1.2 MB · Contract / Agreement / Terms

PDF

QW2.pdf

440.1 KB · Form / Declaration / Certificate

PDF

23592-000-Site Location & Layout Plan.pdf

733.0 KB · Drawing / Plan / Layout

PDF

23592-TEN-100 Boiler Rooms GA.pdf

2.6 MB · Drawing / Plan / Layout

PDF

23592-TEN-110 Main Boiler House.pdf

3.7 MB · Drawing / Plan / Layout

PDF

23592-TEN-200 Hydrotherapy Pool 01.pdf

1.5 MB · Drawing / Plan / Layout

PDF

23592-TEN-210 Hydrotherapy Pool 02.pdf

550.5 KB · Drawing / Plan / Layout

PDF

23592-TEN-300 Kitchen Floor Plan.pdf

697.5 KB · Drawing / Plan / Layout

PDF

23592-TEN-310 Kitchen Fire Barrier Detail.pdf

243.9 KB · Drawing / Plan / Layout

PDF

23592-TEN-400 Door Schedule.pdf

511.7 KB · Drawing / Plan / Layout

PDF

3079-BW-101.pdf

615.9 KB · Drawing / Plan / Layout

PDF

3079-BW-102.pdf

653.3 KB · Drawing / Plan / Layout

PDF

3079-ELEC-301 BOILER HOUSE.pdf

979.3 KB · Drawing / Plan / Layout

PDF

3079-ELEC-303 HYDRO POOL.pdf

664.5 KB · Drawing / Plan / Layout

PDF

3079-ELEC-304 KITCHEN REMOVALS.pdf

2.8 MB · Drawing / Plan / Layout

PDF

3079-ELEC-305 KITCHEN.pdf

778.0 KB · Drawing / Plan / Layout

PDF

3079-ELEC-306 PLANT ROOM ABOVE KTICHEN.pdf

572.5 KB · Drawing / Plan / Layout

PDF

3079-MECH-301 BOILER HOUSE.pdf

633.3 KB · Drawing / Plan / Layout

PDF

3079-MECH-303 KITCHEN.pdf

434.0 KB · Drawing / Plan / Layout

PDF

3079-MECH-701 BOILER HOUSE SCHEMATIC.pdf

654.8 KB · Drawing / Plan / Layout

PDF

DRAFT-21079-CRC-FCC-00-00-DR-YF-1000-RA-REPORT_21.01.2022.pdf

2.0 MB · Drawing / Plan / Layout

PDF

DRAFT-21079-CRC-FCC-00-00-DR-YF-1001-RA-DOORS_21.01.2022.pdf

2.1 MB · Drawing / Plan / Layout

OTHER

plot.log

2.5 KB · Drawing / Plan / Layout

PDF

21079-CRC_RA Report.pdf

1.1 MB · Other

PDF

3079-MECH-302 KITCHEN REMOVALS.pdf

2.1 MB · Other

PDF

Asbestos Management Report.pdf

1.5 MB · Other

PDF

Asbestos Refurbishment Demolition.pdf

1.2 MB · Other

PDF

Cover Letter.pdf

256.0 KB · Other

PDF

21079-CRC_RA doors.pdf

882.4 KB · Appendix / Annex

PDF

Award criteria Evaluation sheet.pdf

282.4 KB · Tender Response Template

XLSX

CRC Alterations 20023.xlsx

89.5 KB

PDF

CRC Remedial Works - M&E Issue Sheet.pdf

276.1 KB · Appendix / Annex

DOCX

QW2-Appendix-D.docx

28.0 KB · Appendix / Annex

DOCX

QW2-Appendix-E.docx

33.2 KB · Appendix / Annex

DOCX

QW2-Appendix-F.docx

32.0 KB · Appendix / Annex

DOCX

QW2-Appendix-G.docx

28.0 KB · Appendix / Annex

DOC

QW2_Appendix_A1.doc

46.5 KB

DOC

QW2_Appendix_A2.doc

54.5 KB

DOC

QW2_Appendix_B1.doc

85.0 KB

DOC

QW2_Appendix_B2.doc

63.0 KB

DOC

QW2_Appendix_B3.doc

67.0 KB

DOC

QW2_Appendix_C1.doc

62.0 KB

DOC

QW2_Appendix_C2.doc

62.5 KB

DOC

QW2_Appendix_C3.doc

63.0 KB

DOC

QW2_Appendix_C4.doc

63.0 KB

DOC

QW2_Appendix_C5.doc

62.0 KB

DOC

QW2_Appendix_C6.doc

61.0 KB

DOC

QW2_Appendix_H.doc

48.5 KB

DOC

QW2_Appendix_I.doc

46.0 KB

DOC

QW2_Supplement_3.4.1.doc

97.5 KB

DOC

QW2_Supplement_3.4.2.doc

111.5 KB

DOC

QW2_Supplement_3.4.3.doc

115.5 KB

DOC

QW2_Supplement_3.4.4.doc

114.5 KB

PDF

Works Proposal.pdf

211.7 KB · Tender Response Template

Original notice text

This tender involves remedial fire works and the upgrade of heating and hydrotherapy pool facilities at the Central Remedial Clinic in Clontarf, focusing on compliance and operational service execution.

AI analysis updated 4 months ago

Bid ↗
Details

Value

€450k

Deadline

19 Jan

View on eTenders ↗

Location

Ireland

Procedure

Open

Clarification

10 Jan 2024

eTenders ID

2816866

✦ Ask AI about this tender

Ask AI

Knows this tender's documents

Is this a good fit for us?
Based on the deadline, buyer, and eligibility requirements in the tender documents, here's a quick read on fit — with citations back to the exact clause 1 so you can verify it yourself.

Example only — sign up to ask about this tender